ASK Gypsum Factory 球磨机执行进度表(沙特)

2019.01.23 合同签订
2019.01.23 Customers place purchase orders
以电汇30%预付和70%根据提单副本付款的付款方式签订合同。
Payment Terms: 30% in advance and 70% by transfer against BL and shipping docs copies


2019.06.15 收到定金30%,开始安排生产
2019.06.15 Received the deposit and start to arrange production.



2019.07.08报关, 订舱
2019.07.08 Clearance of goods, Booking space



2019.07.10 验货
2019.07.10 Inspection of goods


2019.07.19发货
2019.07.19 Shipping



2019.07.25 寄送清关资料
2019.07.25 Send the original shipping documents